Estimating Complex Tasks Accurately
Complex tasks with high uncertainty are notoriously difficult to estimate accurately. GitScrum provides task decomposition tools, historical reference data, and effort tracking that help teams break down complexity into manageable pieces and leverage past performance to improve future estimates.
Simple vs Complex Task Estimation
| Simple Task | Complex Task |
|---|---|
| Well-understood requirements | Ambiguous requirements |
| Done this before | First time attempt |
| Isolated work | Many dependencies |
| Single technology | Multiple systems |
| Clear definition of done | Success criteria unclear |
| Estimate with confidence | Estimate with ranges |
Complex Task Estimation Techniques
TECHNIQUE 1: SPIKE FIRST, ESTIMATE SECOND
Before estimating:
┌─────────────────────────────────────────────────┐
│ 1. Timebox a spike (4-8 hours) │
│ 2. Explore the unknown parts │
│ 3. Document findings │
│ 4. Then estimate with better information │
└─────────────────────────────────────────────────┘
Example:
"We need to integrate with Payment API X"
│
▼
┌─────────────────────────────────────────────────┐
│ Spike: 4 hours to: │
│ • Review API documentation │
│ • Test authentication flow │
│ • Identify edge cases │
│ • Assess SDK quality │
└─────────────────────────────────────────────────┘
│
▼
Now estimate: "3-5 days based on spike findings"
Reference Class Forecasting
TECHNIQUE 2: REFERENCE CLASS
Instead of: "How long will THIS take?"
Ask: "How long did SIMILAR things take?"
REFERENCE DATABASE:
┌─────────────────────────────────────────────────┐
│ Category Avg Time Range │
│ ───────────────────────────────────────────── │
│ Payment integration 8 days 5-15 days │
│ OAuth implementation 5 days 3-8 days │
│ Data migration 12 days 7-21 days │
│ New API endpoint 2 days 1-4 days │
│ Third-party API 6 days 3-12 days │
│ Performance fix 4 days 2-10 days │
└─────────────────────────────────────────────────┘
APPLICATION:
"New Stripe integration estimate?"
→ Reference: Payment integrations average 8 days
→ This one: Similar complexity
→ Estimate: 8 days (range: 5-12 days)
Three-Point Estimation
TECHNIQUE 3: PERT ESTIMATION
For each complex task, estimate three scenarios:
O = Optimistic (best case, 10% likely)
M = Most Likely (normal case, 80% likely)
L = Pessimistic (worst case, 10% likely)
PERT Estimate = (O + 4M + L) / 6
EXAMPLE:
┌─────────────────────────────────────────────────┐
│ Task: Implement SSO with customer's IdP │
│ │
│ Optimistic (O): 3 days │
│ (IdP is standard, good docs, quick IT) │
│ │
│ Most Likely (M): 7 days │
│ (Some config issues, normal back-and-forth) │
│ │
│ Pessimistic (L): 15 days │
│ (Non-standard setup, slow IT, edge cases) │
│ │
│ PERT = (3 + 4×7 + 15) / 6 = 7.67 days │
│ Report: "7-8 days, could range 3-15" │
└─────────────────────────────────────────────────┘
Decomposition
TECHNIQUE 4: BREAK IT DOWN
Complex Task: "Build reporting dashboard"
Level 0 (Too vague to estimate):
┌─────────────────────────────────────────────────┐
│ "Build reporting dashboard" = ??? │
└─────────────────────────────────────────────────┘
Level 1 (Better):
┌─────────────────────────────────────────────────┐
│ 1. Data pipeline setup 3-5 days │
│ 2. Chart components 2-3 days │
│ 3. Filtering system 2-4 days │
│ 4. Export functionality 1-2 days │
│ 5. Performance optimization 2-3 days │
│ ─────────────────────────────────────────── │
│ Total: 10-17 days │
└─────────────────────────────────────────────────┘
Level 2 (Actionable):
┌─────────────────────────────────────────────────┐
│ 1. Data pipeline setup: │
│ a. Database queries (1 day) │
│ b. Aggregation logic (1-2 days) │
│ c. Caching layer (1-2 days) │
│ Total: 3-5 days │
└─────────────────────────────────────────────────┘
Rule: Estimate tasks no larger than 2-3 days
Best Practices
- Spike before estimating high-uncertainty work
- Use historical data from similar past work
- Estimate in ranges with confidence levels
- Decompose until estimable (2-3 day chunks)
- Identify assumptions and risks explicitly
- Re-estimate at checkpoints as you learn
- Involve the team doing the work
- Document reasoning not just numbers
Anti-Patterns
✗ Single-point estimates for complex work
✗ Estimating without understanding
✗ Ignoring historical data
✗ Not accounting for dependencies
✗ Pressure to give low estimates
✗ No re-estimation as scope changes