Try free
6 min read Guide 174 of 877

Estimating Task Duration Accurately

Accurate estimation is essential for planning but notoriously difficult. Most estimates are optimistic because they assume everything goes right. Better estimation combines historical data, decomposition, collaborative input, and explicit uncertainty ranges.

Estimation Challenges

Why Estimates FailHow to Improve
Optimism biasAdd explicit buffer
Unknown unknownsDecompose smaller
Scope creepDefine scope clearly
Skipped stepsInclude all work
Individual variationTeam estimation

Estimation Techniques

Decomposition

TASK DECOMPOSITION
══════════════════

ORIGINAL ESTIMATE:
"Build login feature" - 3 days ❌ Too vague

DECOMPOSED:
─────────────────────────────────────
"Build login feature"
├── Design API endpoints          2h
├── Implement backend auth       4h
├── Write unit tests             2h
├── Create frontend form         3h
├── Frontend validation          1h
├── Connect frontend to API      2h
├── End-to-end tests             2h
├── Error handling               2h
├── Code review cycles           2h
├── Bug fixes from review        2h
├── Documentation update         1h
├── Deploy and verify            1h
─────────────────────────────────────
TOTAL: 24h = 3 days coding
+ Buffer (30%): 7h
= 4 days realistic ✓

DECOMPOSITION RULE:
├── No task > 4 hours
├── If bigger, decompose further
├── Include non-coding tasks
└── Be specific, not vague

Historical Comparison

USING HISTORICAL DATA
═════════════════════

SIMILAR PAST TASKS:
─────────────────────────────────────
Feature Type: User form with API
Past Examples:
├── Registration form: Est 3d → Actual 4d
├── Profile update: Est 2d → Actual 3d
├── Settings page: Est 2d → Actual 2.5d
─────────────────────────────────────
Average actual/estimate ratio: 1.4x

NEW ESTIMATE:
Login feature estimate: 3 days
Calibrated estimate: 3 × 1.4 = 4.2 days
Round up: 5 days

TRACKING CALIBRATION:
├── Record estimate for each task
├── Record actual time spent
├── Calculate ratio over time
├── Use ratio to calibrate
└── Improve ratio over time

Team Estimation

PLANNING POKER
══════════════

PROCESS:
1. Present task to team
2. Clarify requirements
3. Everyone estimates silently
4. Reveal estimates simultaneously
5. Discuss differences
6. Re-estimate until convergence

FIBONACCI SCALE:
├── 1, 2, 3, 5, 8, 13, 21, ?
├── Gap increases with size
├── Reflects uncertainty
└── ? = Too big, needs decomposition

EXAMPLE SESSION:
─────────────────────────────────────
Task: "Add OAuth login"
Round 1: Sarah: 5, Mike: 8, Alex: 13

Discussion:
Sarah: "Simple library integration"
Mike: "Need error handling, tests"
Alex: "Don't forget multiple providers"

Round 2: Sarah: 8, Mike: 8, Alex: 8
Consensus: 8 points ✓
─────────────────────────────────────

Three-Point Estimation

THREE-POINT ESTIMATES
═════════════════════

FOR EACH TASK:
├── Optimistic (O): Everything goes right
├── Most Likely (M): Normal conditions
├── Pessimistic (P): Things go wrong

PERT FORMULA:
Estimate = (O + 4M + P) / 6

EXAMPLE:
─────────────────────────────────────
Task: Implement search feature

Optimistic: 2 days (simple requirements, no bugs)
Most Likely: 4 days (normal development)
Pessimistic: 8 days (complex edge cases, rework)

PERT Estimate = (2 + 4×4 + 8) / 6 = 4.3 days

REPORT AS RANGE:
"4-5 days, could be up to 8 if complications"
─────────────────────────────────────

WHEN TO USE RANGES:
├── High uncertainty tasks
├── New technology
├── Unclear requirements
├── External dependencies
└── Stakeholder communication

Estimation Process

Complete Task Estimation

COMPLETE ESTIMATION CHECKLIST
═════════════════════════════

FOR EVERY ESTIMATE, INCLUDE:

□ DEVELOPMENT TIME
  ├── Coding
  ├── Local testing
  └── Debugging

□ QUALITY TIME
  ├── Unit tests
  ├── Integration tests
  ├── Code review (multiple cycles)
  └── Bug fixes from review

□ INTEGRATION TIME
  ├── Merge conflicts
  ├── CI/CD pipeline
  ├── Staging testing
  └── Production deploy

□ DOCUMENTATION
  ├── Code comments
  ├── API documentation
  ├── User documentation
  └── Internal notes

□ COMMUNICATION
  ├── Clarification meetings
  ├── Status updates
  ├── Demo preparation
  └── Handoff

□ BUFFER
  ├── Unknown issues (30% default)
  ├── Meetings/interruptions
  ├── Context switching
  └── Energy variation

Sprint Capacity

SPRINT CAPACITY CALCULATION
═══════════════════════════

AVAILABLE HOURS:
─────────────────────────────────────
Working days: 10
Hours per day: 8
Total: 80 hours

SUBTRACT OVERHEAD:
├── Meetings (avg): -10 hours
├── Email/Slack: -5 hours
├── Code reviews: -5 hours
├── Unplanned work: -5 hours
├── Context switching: -5 hours
─────────────────────────────────────
Productive coding: 50 hours (62%)

PLAN AT 70% OF PRODUCTIVE:
50 × 0.7 = 35 hours planned

WHY 70%:
├── Estimates are optimistic
├── Unknowns happen
├── Leave room for quality
├── Sustainable pace
└── Better to under-promise

TEAM CAPACITY:
5 developers × 35 hours = 175 hours
Buffer maintained at team level

GitScrum for Estimation

Tracking Estimates

GITSCRUM ESTIMATION FEATURES
════════════════════════════

ESTIMATE FIELD:
├── Add estimate when creating task
├── Story points or hours
├── Required before sprint

ACTUAL FIELD:
├── Log time spent
├── Automatic or manual
├── Compare to estimate

ESTIMATION REPORT:
─────────────────────────────────────
Task          Estimate    Actual    Ratio
─────────────────────────────────────
GS-123        5 pts       7 pts     1.4x
GS-124        3 pts       3 pts     1.0x
GS-125        8 pts       12 pts    1.5x
─────────────────────────────────────
Average ratio: 1.3x

Use 1.3x to calibrate future estimates

VELOCITY TRACKING:
├── Points completed per sprint
├── Trend over time
├── Predictable planning basis
└── Adjust capacity based on velocity

Best Practices

For Accurate Estimates

  1. Decompose first — Break down before estimating
  2. Use history — Calibrate with past data
  3. Estimate together — Team wisdom
  4. Include everything — Not just coding
  5. Track and learn — Improve over time

Anti-Patterns

ESTIMATION MISTAKES:
✗ Coding time only (no tests, review)
✗ Optimistic assumptions
✗ No decomposition
✗ Individual estimates for team
✗ Never tracking actual vs. estimate
✗ Treating estimates as commitments
✗ No buffer for unknowns
✗ Pressure to underestimate